Pennsylvania Mechanic's Lien Deadline
| Project | Deadline | Statute |
|---|---|---|
| Private - commercial | 6 months | 49 P.S. §1502(a)(1) |
| Private - residential | 6 months | 49 P.S. §1502; §1303(d) |
| Public project (bond claim - no lien) | 90 days | 8 P.S. §194 (Public Works Contractors' Bond Law) |
How long do I have to file a mechanic's lien in Pennsylvania?
Private - commercial: 6 months (49 P.S. §1502(a)(1)); Private - residential: 6 months (49 P.S. §1502; §1303(d)); Public project (bond claim - no lien): 90 days (8 P.S. §194 (Public Works Contractors' Bond Law))
Do I need a Notice of Intent in Pennsylvania?
If you were not hired directly by the property owner, a Notice of Intent is generally required before the lien can be filed, and it has its own strict deadline - the calculator on this page shows it. Missing it can void your lien. Speedy Lien prepares and serves the Notice of Intent for you. Contractors hired directly by the owner don't need one.
What if the deadline falls on a weekend or holiday?
Our calculator shows the PRIOR business day as your deadline when the statutory date falls on a weekend or legal holiday, so you don't risk filing late. The original statutory date is shown for reference.
Do I have to serve the lien in Pennsylvania?
Some projects require a notice before the lien can be filed, with its own deadline. Speedy Lien handles these for you. After filing, the lien must be served on the owner and other required parties, and proof of service filed, within strict deadlines. Missing a step can void your lien. Speedy Lien handles filing and service for you. Call 212-203-7420 ext 104 or start your filing online - we take care of every step.
How long does a Pennsylvania lien last?
Writ of scire facias (action to obtain judgment) must be filed within 2 years after the lien is filed; verdict within 5 years (§1701, §1711). Speedy Lien can refer you to an attorney to enforce the lien, file a judgment, or even foreclose on the lien. (Pennsylvania law does not provide for extending a lien, so enforcement deadlines are firm.)
Calculate your Pennsylvania deadline
Need help filing?
Speedy Lien files and serves mechanic’s liens in NY, NJ, CT & PA.
Get started with Speedy Lien →Speedy Lien, Inc.
Phone: 212-203-7420 ext 104
Email: Admin@SpeedyLienInc.com
Website: www.SpeedyLienInc.com
Get deadline reminders
We'll email you 90, 60, 30 and 14 days before your deadline (calculate your deadline first).