New York Mechanic's Lien Deadline

ProjectDeadlineStatute
Private - single-family home or condo unit4 monthsN.Y. Lien Law §10(1)
Private - 2-family+ / multi-family / commercial8 monthsN.Y. Lien Law §10(1)
Public improvement30 daysN.Y. Lien Law §12

How long do I have to file a mechanic's lien in New York?

Private - single-family home or condo unit: 4 months (N.Y. Lien Law §10(1)); Private - 2-family+ / multi-family / commercial: 8 months (N.Y. Lien Law §10(1)); Public improvement: 30 days (N.Y. Lien Law §12)

What if the deadline falls on a weekend or holiday?

Our calculator shows the PRIOR business day as your deadline when the statutory date falls on a weekend or legal holiday, so you don't risk filing late. The original statutory date is shown for reference.

Public improvement: what should I know?

There is no specific fixed date: completion and acceptance by the public entity is uncertain and often not announced. Waiting may cause you to miss the deadline - file as early as possible.

Do I have to serve the lien in New York?

After filing, the lien must be served on the owner and other required parties, and proof of service filed, within strict deadlines. Missing a step can void your lien. Speedy Lien handles filing and service for you. Public improvement liens have their own filing and service requirements; Speedy Lien handles those too. Call 212-203-7420 ext 104 or start your filing online - we take care of every step.

How long does a New York lien last?

Lien lasts 1 year from filing unless an action to foreclose is started with a notice of pendency, or the lien is extended (§17). Public lien: 1 year, extendable by court order (§18). Extensions (NY Lien Law §17): a commercial lien (2-family+ / multi-family / commercial, 8-month category) can be extended 3 times before a foreclosure action is required - first a filed commercial extension, then 2 signed-order extensions. A single-family home or condo unit lien (4-month category) can be extended only by 2 signed-order extensions. A signed-order extension requires Speedy Lien to hire an attorney to petition the court and a judge to sign an order extending the lien. Speedy Lien handles extensions. Speedy Lien can refer you to an attorney to enforce the lien, file a judgment, or even foreclose on the lien. Speedy Lien also handles lien extensions. We also follow up with you prior to the deadline as part of our service.

Calculate your New York deadline

Need help filing?

Speedy Lien files and serves mechanic’s liens in NY, NJ, CT & PA.

Get started with Speedy Lien →

Speedy Lien, Inc.
Phone: 212-203-7420 ext 104
Email: Admin@SpeedyLienInc.com
Website: www.SpeedyLienInc.com

Get deadline reminders

We'll email you 90, 60, 30 and 14 days before your deadline (calculate your deadline first).

Privacy: We only use your email to send your lien deadline reminders. Unsubscribe anytime with one click from any reminder. We never sell or share your email.